Road Construction Update: 6-29-18

The latest update: Due to the extreme heat conditions this weekend, The crews have been authorized work to begin at 6 a.m. both Saturday and Sunday. The project is progressing well today. As of 12:30 p.m., the eastbound lanes have been paved, now starting the center...

Road Construction Update; 6-27-18

We’re nearing the finish line on the road project! Here’s t:he latest update from the Engineering Department: Due to the heavy rains today we are pushing back tomorrows scheduled paving to Friday. There will no doubt be some areas of ponding water tomorrow...

Road Construction Update; 5-19-18

The latest from the Engineering Department…. The project is on track for paving next week and then work will start on the opposite side of the roads. The traffic switch will occur on May 29 and the milling off of asphalt on south 14 Mile and west Main Street...

Road Construction Update 5-14-18

Due to weather and other factors the project is one week behind the July 1st completion date. We will post more information after the May 17 construction meeting. Meanwhile we have photos… Some happy news when tracks from the Interurban train were uncovered on...