The latest from the Engineering Department on the road resurfacing project:

No Major changes with the 14 Mile & Main St. project. We had a field meeting this morning and everything is on track for milling off the old asphalt on westbound 14 Mile and northbound Main St. on Monday morning. I made a switch with street closures to improve traffic circulation. Florence is now open at 14 Mile and Bowers at Main St. High St. is Closed at 14 Mile to minimize cut through traffic and allow for intersection repairs.  This allows better circulation around the N.W. Parking lot and the Ace Hardware complex. I met with the manager from Ace Hardware this afternoon to coordinate delivery concerns and traffic flow. So far things are slower as expected, but working. We will be working with businesses as best as possible to minimize interruptions.

Thanks,
Harry G. Drinkwine